• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2020 - Dec 2020
  • Estimated project cost $203,886
  • Australian Government contribution $203,886
  • Local Council/Shire Newcastle City Council
  • State NSW

Project description

Failed road pavement beyond intervention on regular bus and school route.

Replacement and upgrade of existing road pavement to suit current traffic loading, work includes kerb and gutter and associated road infrastructure

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.