• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Early 2022 - Early 2023
  • Estimated project cost $25,000,000
  • Australian Government contribution $20,000,000
  • Local Council/Shire Shire of Chittering,Shire of Gingin
  • State WA

Project description

Over a 45 km section of the Brand Highway, the project will:

  • Rehabilitate (granular overlay) 30 km of pavement; and
  • Widen 27 km including wide audible centreline from Muchea to the Gingin turnoff.

The project complements the recently completed NorthLink WA project.

Benefits

  • Improved road safety for all road users
  • Improved efficiency and network reliability
  • Improved accessibility and connectivity of road networks

Funding

The Australian Government has committed $20 million towards the $25 million project.

Timetable

Construction commenced in April 2022 and was completed in April 2023.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.