• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Early 2022 - Early 2023
  • Estimated project cost $35,000,000
  • Australian Government contribution $28,000,000
  • Local Council/Shire Shire of Boddington,Shire of Wandering
  • State WA

Project description

The project will:

  • Rehabilitate the pavement on 29 km over various sections between Kelmscott and Williams upgrading the sections of road subject to regular pavement failures
  • Replace the ageing Hotham River Bridge with a new concrete structure to current width and barrier standards which will improve safety

Benefits

  • Improved efficiency and network reliability
  • Improved accessibility and connectivity of road networks
  • Improved road safety for all road users

Funding

The Australian Government has committed $28 million towards the $35 million project.

Timetable

Construction commenced in early 2022 and was completed in early 2023.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.