• Funding program Investment Road and Rail Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Early 2023 - Late 2027
  • Estimated project cost $298,500,000
  • Australian Government contribution $139,250,000
  • Local Council/Shire Brisbane City Council
  • State QLD

Project description

This project is expected to deliver a new bridge west of the existing Centenary Bridge, as part of the staged upgrade to the motorway.
 

Key works include:
A new three-lane northbound bridge
Remediation of the existing bridge to accommodate three lanes

 

Benefits

The project is expected to deliver:

Reduced congestion.

Improved travel times.
Improved connectivity between people with jobs and services, and goods with markets.
Improved active transport facilities
Improved flood immunity

Funding

The Australian Government has committed $139.25 million towards the project.

Timetable

The project commenced construction in early 2023 and is expected to be complete late 2027.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.