• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2020 - Mar 2021
  • Estimated project cost $78,409
  • Australian Government contribution $78,409
  • State NSW

Project description

The existing road surface is old and brittle. It has been affected by cracks, delamination and pavement failures. Due to cracks and other pavement defects, the road is very rough with high amount of loose aggregate.

The proposed work will include repair of pavement defects by heavy patching and resurfacing of the road. Length = 228 m; Width = 9.8 m; Area = 2234.4 m2.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.