• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2020 - Feb 2021
  • Estimated project cost $437,605
  • Australian Government contribution $437,605
  • Local Council/Shire Penrith City Council
  • State NSW

Project description

The road was originally constructed in 1977 and is already failed with numerous potholes and patching due to the increasing commercial traffic and inadequate pavement materials.

It is proposed to mill a pavement to a depth of 150mm and to fill with asphalt for a length of 362 metres and a width of 12.1 metres.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.