• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2020 - Apr 2021
  • Estimated project cost $295,834
  • Australian Government contribution $295,834
  • Local Council/Shire Shire of Kent
  • State WA

Project description

Major blowouts that are being continuously repaired, these are caused by the clay sub base. This problem creates rough bituminous surface which is dangerous to road users. This road is high traffic, major grain truck route and school bus route.

Lime stabilise sub base; fresh gravel sheet on top of sub base; cement stabilise pavement; improve drainage and reseal. Install signage and guideposts.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.