• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2021 - Jun 2021
  • Estimated project cost $108,539
  • Australian Government contribution $108,000
  • Local Council/Shire King Island Council
  • State TAS

Project description

Widen road from 3 meters to 6 meters for better access for tourist bus & 2 wheel drive tourist cars and provide all the year round access. This is one of the top areas on the island visited by tourists and surfers.

Widen road from 3 meters to 6 metres. Remove banks & some bush areas and improve drainage by installing culvert pipes. Place 200 mm of gravels and compact .

Total cost of proposed project is $108,539

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.