• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2020 - Nov 2020
  • Estimated project cost $41,107
  • Australian Government contribution $41,107
  • Local Council/Shire City of Belmont
  • State WA

Project description

Road is part of a small subdivision of three streets and is showing excessive asphalt cracking due to the age of the wearing course. To prevent future costly damage to the base course material by the ingress of stormwater a new overlay is proposed.

Length, width and area of job: 193m x 6.0m = 1,285m2. Existing asphalt surface is to be profiled off over full length of the road, minor kerb damaged to repaired and minor crossover faults to be corrected. Road is then to have a new full length asphalt wearing course applied to it.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.