• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2021 - May 2021
  • Estimated project cost $64,154
  • Australian Government contribution $64,154
  • Local Council/Shire Shire of Tammin
  • State WA

Project description

Currently the pavement width is approximately 7m with a sealed lane of a 4m width in the centre. The road is too narrow and the seal is deteriorating beyond its useful life. The narrowness of the road result in vehicular conflict when passing.

It is proposed to widen the current pavement to a width of 10m, stabilising on the pavement to a depth of 175mm and seal the new pavement with a prime coat and 2 coat seal finish. Finally, reinstatement of road furniture and signs.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.