• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2021 - May 2024
  • Estimated project cost $5,992,773
  • Australian Government contribution $592,773
  • Local Council/Shire Griffith City Council
  • State NSW

Project description

Road has high volumes of dust causing poor visibility and corrugations in dry conditions and can be impassable in wet conditions, making road safety an issue

Construct and seal Boorga Road (6.7km), install additional drainage culverts and table drains. Pavement seal width including 2.0m sealed shoulder is 11.0m

Total cost of proposed project is $5,992,773

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.