• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2021 - May 2021
  • Estimated project cost $364,635
  • Australian Government contribution $346,718
  • Local Council/Shire Shire of Kulin
  • State WA

Project description

Flooding and drainage issues, pavement and surface failure

Installation of underground drainage pipes and catch pits. Reconstruction and reshaping of road pavement and resurfacing with asphalt. New kerbs and footpath reinstatement with pram ramps

Total cost of proposed project is $364,635

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.