• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2021 - Jun 2021
  • Estimated project cost $401,605
  • Australian Government contribution $247,855
  • State NSW

Project description

Existing sealed surface is in poor condition with pavement fails in number of spots and has been subject of high yearly maintenance costs. Narrow culverts and poor drainage to be improved.

Lime Stabilise existing subbase and overlay with gravel to strengthen the road. Old drainage pipes across the road will be replaced by box culvert to improve the drainage and safety of vehicle run off from the road.

Total cost of proposed project is $401,605

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.