• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2022 - Jun 2022
  • Estimated project cost $620,000
  • Australian Government contribution $201,890
  • Local Council/Shire Ku-Ring-Gai Council
  • State NSW

Project description

Section of the road is in a poor condition with several crocodile cracking, rutting and high roughness causing safety concerns to the road users. Council have received several request to improve the road and details investigation confirmed that pavement structure is required significant improvement to meet the level of service for the community.

Reconstruct the pavement structure between Stanhope Road and Rosebery Road. Excavate total of 150mm thick of existing pavement and reconstruct with 100mm of AC28 and 50mm of AC14 as wearing course. Project includes reinstatement to the existing line marking and Road Pavement Markings as part of the reconstruction works.

Total cost of proposed project is $620,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.