• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2021 - Aug 2022
  • Estimated project cost $327,214
  • Australian Government contribution $50,000
  • Local Council/Shire Walcha Council
  • State NSW

Project description

Forest Way is in unsealed road that suffers severe pavement deformations during wet weather periods due to large amounts of heavy vehicle movements.

Works will involve a gravel overlay and in situ stabilisation of the existing pavement, followed by a 14/7mm double/double seal.

Total cost of proposed project is $327,214

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.