• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2021 - Jun 2022
  • Estimated project cost $644,763
  • Australian Government contribution $200,000
  • State NSW

Project description

Culvert slumping and creating a hazard

Replace multi-span culvert with single-span concrete bridge

Total cost of proposed project is $644,763

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.