• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2021 - Mar 2022
  • Estimated project cost $521,819
  • Australian Government contribution $479,000
  • Local Council/Shire Junee Shire Council
  • State NSW

Project description

The pavement has extensive failures such as shoving and rutting along this section of the road. This pavement width is currently 6m. It is very difficult for vehicles pass each other safely in this narrow section of the road.

The project includes traffic control, lime stabilisation applying 100mm overlay, applying 14/7mm sprayed bituminous seal, installation of new drains and linemarking.

Total cost of proposed project is $521,819

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.