• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jan 2021 - Apr 2021
  • Estimated project cost $263,376
  • Australian Government contribution $236,702
  • Local Council/Shire Gunnedah Shire Council
  • State NSW

Project description

Road surface is narrow, deformed and breaking up. The road is unsafe for all stakeholders particularly for the school bus due to the increase heavy vehicle activity on the road

Rip and shape existing pavement to a depth of 150, strengthen and widen pavement by adding 100mm over and stabilising gravel overlay. Sealing of the entire reconstructed section with a waterproof wearing surface

Total cost of proposed project is $263,376

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.