• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2021 - Dec 2021
  • Estimated project cost $176,869
  • Australian Government contribution $176,869
  • Local Council/Shire Campbelltown City Council
  • State NSW

Project description

The road pavement is affected with structural cracking, potholes with pumping of fines. The length of affected road section is 280m, width 12.5m and area of 3552m2.

The pavement will be rehabilitated with insitu stabilisation followed by seal with hot-mix asphalt overlay.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.