• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Sep 2021 - Dec 2021
  • Estimated project cost $95,000
  • Australian Government contribution $80,000
  • Local Council/Shire Southern Mallee District Council
  • State SA

Project description

Hamilton Road being a clay road is impassable when wet

Construct an all weather rubble road on Hamilton Road on a road length of 2.4 Kilometers , widening to a width of 7.2 meters by providing 150mm of compacted rubble

Total cost of proposed project is $95,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.