• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2021 - Apr 2022
  • Estimated project cost $1,100,000
  • Australian Government contribution $800,000
  • Local Council/Shire City of Salisbury
  • State SA

Project description

Mawson Lakes Boulevard has experienced load induced failure due to high traffic volumes and traffic load there is segmental cracking throughout the road seal. The wearing surface has oxidised and become brittle and falling away

Profile and Reinstate the Asphalt wearing course with flexible mesh geogrid to reinforce the asphalt layers

Total cost of proposed project is $1,100,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.