• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2022 - Jul 2022
  • Estimated project cost $163,504
  • Australian Government contribution $33,602
  • Local Council/Shire Bland Shire Council
  • State NSW

Project description

Lake Cowal Road requires extensive remediation. Defects include potholes, corrugations, rutting, depressions and gravel loss. Maintenance work is required to bring the road back to an acceptable level of service for the community.

The road requires minimum of 75mm gravel resheet and shape correction for 5.1km, and wet grading for 21.6km to improve road shape. Table drains and mitre drains will also be reshaped as necessary to improve drainage.

Total cost of proposed project is $163,504

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.