• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2022 - Sep 2022
  • Estimated project cost $256,846
  • Australian Government contribution $162,000
  • State NSW

Project description

Melville Street pavement has extensive failure approximately 60% of the area. Pavement length is 220m and average width is 11m. Kerb and gutter has failed for approximately 30% of the length.

Rehabilitation of the pavement by heavy patching, profiling and resurfacing. Replacement of failed kerb and gutter.

Total cost of proposed project is $256,846

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.