• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2022 - Jun 2023
  • Estimated project cost $1,513,339
  • Australian Government contribution $311,924
  • Local Council/Shire Carpentaria Shire Council
  • State QLD

Project description

Flood immunity and vehicle safety. Realigning an unsafe section of road.

Realignment of a section of the road and install larger culverts. This section is currently unsafe and has limited visibility due to the dip and curve of the road. Council are going to install new, larger culverts to increase the flood immunity and realign the section of road to drastically improve the safety and visibility of the section of road. Works will include new culverts, road realignment and pavement stabilisation, bitumen sealing and drainage works.

Total cost of proposed project is $1,513,339

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.