• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2023 - Jun 2024
  • Estimated project cost $123,136
  • Australian Government contribution $123,136
  • Local Council/Shire Bourke Shire Council
  • State NSW

Project description

NAmoi Street ahs been constructed in gravel but never sealed. This causes problems to the residents who have to access their property during and after wet weather events. The pavement rapidly deteriorates under traffic in wet weather, causing problems for the residents trying to access their properties and for Council trying to maintain the road.

Add additional gravel to the unsealed road and mix it in to the existing gravel pavement. Compact the mixed material to match the existing levels of the sealed pavement and the kerb and gutter. Provide a temporary 7 mm bitumen emulsion Primer seal followed by a later 10mm hot bitumen spray Final seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.