• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Mar 2024 - Jun 2024
  • Estimated project cost $760,576
  • Australian Government contribution $423,695
  • Local Council/Shire City of Glen Eira
  • State VIC

Project description

A recent site inspection and condition assessment indicated that the road is uneven; Kerb & channel are in dilapidated condition and need reconstruction. About 470m long kerb & channel and 2000sqm of roads need renewal as they are showing signs of failure. Vehicle crossovers damaged as well as some scraping of road pavement.

The work involves installing new kerb and channel, reconstructing failed pavement sections, installing underground drains, filling drainage trenches and constructing pavements, providing adequate drainage to the street and asphalt surfacing.

Total cost of proposed project is $760,576

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.