• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2025 - May 2025
  • Estimated project cost $350,000
  • Australian Government contribution $100,000
  • Local Council/Shire Goulburn Mulwaree Council
  • State NSW

Project description

Existing bitumen sealed road is narrow in width creating issues for passing vehicles. Road is also showing signs of rutting and creating safety concerns for motorists.

It is proposed to widen the carriage way to 8 m with 100 mm gravel overlay and stabilization of the pavement with new 8 m bitumen seal. Council to co-contribute $250,000 from Rural Road Rehabilitation General funds.

Total cost of proposed project is $350,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.