• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2025 - Mar 2025
  • Estimated project cost $250,000
  • Australian Government contribution $164,621
  • Local Council/Shire Shire of Halls Creek
  • State WA

Project description

Road formation and the unsealed gravel surface is worn, degraded and losing shape. The existing roadside drainage requires reshaping and renewal. Additional funding to be provided by council funds.

Reform and re-sheet the road formation and renew the existing roadside drainage including table drains and offshoot drains. The project will be partly funded by Remote Access Road funding administered by Main Roads WA and the Shire's own source municipal funds.

Total cost of proposed project is $250,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.