• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2024 - Mar 2025
  • Estimated project cost $472,023
  • Australian Government contribution $259,126
  • Local Council/Shire Yarra City Council
  • State VIC

Project description

Asphalt road surface deterioration (oxidation, rutting, crack removal), pothole removal and reshaping road profile including footpath and kerb and channel renewal.

Road pavement rehabilitation. Asphalt road resurfacing. Partial roto-milling and disposal of old surface and resurfacing with bitumen. Install deep lift asphalt in selected areas including footpath and kerb and channel renewal. Project cost to be part funded by council cash.

Total cost of proposed project is $472,023

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.