• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Feb 2025 - Jun 2025
  • Estimated project cost $166,883
  • Australian Government contribution $166,883
  • Local Council/Shire City of Bunbury
  • State WA

Project description

Significant cracking, broken kerbing and damaged drainage creating depressions in the road.

Replace drainage crossing and upgrade drainage pits, replace kerbing, profile existing bitumen surface and install new asphalt seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.