• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2024 - Dec 2024
  • Estimated project cost $215,772
  • Australian Government contribution $215,772
  • Local Council/Shire Randwick City Council
  • State NSW

Project description

Asphalt road asset is at end of life e.g. wearing surface defect (potholes, stripping), base course defects (crocodile cracking and block cracking), causing a slippery when wet driving surface and rough rideability for commuters.

Isolated 100 mm AC20 heavy patching and 50 mm AC10 wearing course replacement across the full width and entire extent of project.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.