• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jul 2024 - Dec 2024
  • Estimated project cost $160,772
  • Australian Government contribution $160,772
  • Local Council/Shire Randwick City Council
  • State NSW

Project description

Asphalt road at end of life, e.g. potholes, crocodile cracking etc. Isolated sections of kerb and gutter at end of life and causing drainage issue during high precipitation events for commuters and surrounding residents.

Reconstruction of old, dilapidated kerb and gutter and 40 mm AC10 re-sheeting of the road, entire width, full extent.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.