• Funding program Roads to Recovery Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Mar 2025 - Nov 2025
  • Estimated project cost $370,000
  • Australian Government contribution $295,976
  • Local Council/Shire Alexandrina Council
  • State SA

Project description

The major culvert is at the end of its useful life and has reached the intervention point for renewal. Problems being addressed include: severely deteriorated deck and culvert, poor approach and departure alignments.

Remove the existing culvert and decks and replace with new, plus re-aligning the approach and departure alignment to improve traffic safety and sight lines.

Total cost of proposed project is $370,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.