• Funding program Investment Road and Rail Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Mid 2025 - Mid 2026
  • Estimated project cost $22,500,000
  • Australian Government contribution $8,500,000
  • State VIC

Project description

The Goulburn Valley Link Freight Precinct project will deliver enabling works, including road connections into the Goulburn Valley Link Freight Precinct in order to facilitate High Productivity Freight Vehicle movements, 

Benefits

The project will support the delivery of industrial lots, improve transport connections, construction of a new roundabout and upgrading of supporting infrastructure, improving access for High Productivity Freight Vehicles and enable associated industries to support local and regional economic growth.

Funding

The Australian Government has committed $8.5 million and the Greater Shepparton City Council has committed $14.4 million towards the project.

Timetable

Construction is expected to commence in mid-2025 with an estimated completion date of mid-2026.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.