• Funding program Roads to Recovery Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Jan 2025 - Sep 2025
  • Estimated project cost $787,000
  • Australian Government contribution $320,000
  • Local Council/Shire West Tamar Council
  • State TAS

Project description

Road has deteriorated with undulations, break up and potholing of the surface. Roadsides have no defined stormwater drainage.

Full digout and rebuild 410 metres of sealed road approximately 8.5 metres wide. Concrete vee drains each side of road diverting stormwater into new pits and pipework. Existing swale drains to be infilled. Forming 21 concrete driveways and crossings to replace the existing. Additional funding provided by West Tamar Council.

Total cost of proposed project is $787,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.