• Funding program Roads to Recovery Program
  • Status In planning
  • Transport mode Road
  • Expected start/finish Oct 2025 - Dec 2025
  • Estimated project cost $110,000
  • Australian Government contribution $110,000
  • Local Council/Shire Belyuen Community Goverment Council
  • State NT

Project description

Deteriorating roads, washouts, potholes, shoulder erosion, inadequate signage.

Replace 2.5 km of internal sealed roads in Belyuen community including shoulder works, line marking, speed bumps and signage.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.