• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2024 - May 2025
  • Estimated project cost $1,978,343
  • Australian Government contribution $1,777,273
  • Local Council/Shire Ipswich City Council
  • State QLD

Project description

Road asset has reached the end of useful life and requires reconstruction with ongoing maintenance activities being requirement to keep road operational.

Undertake road pavement reconstruction works on sections of Jasmine Street. The Balance of funds required for theproject will be sourced from Ipswich City Council funds

Total cost of proposed project is $1,978,343

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.