• Funding program Roads to Recovery Program
  • Status In planning
  • Transport mode Road
  • Expected start/finish Feb 2026 - Jul 2026
  • Estimated project cost $3,100,000
  • Australian Government contribution $1,308,775
  • Local Council/Shire Kingston City Council,Kingston District Council
  • State VIC

Project description

Flexible road pavement is in poor condition – it has extensive crocodile cracking and heaving failures. Due to required drainage upgrade works as part of this project, with the drain to be constructed underneath this road, the road pavement will require full reconstruction.

Works will include the reconstruction of the road pavement, drainage, vehicle crossings and footpaths and kerb and channel. Council funds will be used as the additional source of funding.

Total cost of proposed project is $3,100,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.