• Funding program Roads to Recovery Program
  • Status In planning
  • Transport mode Road
  • Expected start/finish Jan 2026 - Feb 2026
  • Estimated project cost $349,214
  • Australian Government contribution $349,214
  • State WA

Project description

The 40-year-old road seal and kerb is in a very poor condition being severely worn and aged. The road drainage also needs to be improved. The end of the road is small and does not allow for large vehicle turn around.

The road will be re-profiled and given an asphalt overlay with the construction of cul-de-sac at the end. There will also be drainage improvements, and the kerb will be replaced.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.