• Funding program Roads to Recovery Program
  • Status In planning
  • Transport mode Road
  • Expected start/finish Mar 2026 - Apr 2026
  • Estimated project cost $381,923
  • Australian Government contribution $381,923
  • Local Council/Shire Swan Hill Rural City Council,City of Swan
  • State WA

Project description

The roundabout at the intersection of West Swan Road and Benara Road scored an average surface condition of 5 out of 5 (with 5 being very poor). The roundabout has been patched and visual inspections confirm the presence of structural cracking in the roundabout. Pavement testing and modeling indicate road pavement rehabilitation is required to rectify the following issues.

In situ foamed bitumen stabilisation to a depth of 370 mm, profile off top 40 mm material, apply 7 mm granite primer seal, and lay 40 mm new asphalt concrete wearing.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.