• Funding program Roads to Recovery Program
  • Status Under construction
  • Transport mode Road
  • Expected start/finish Oct 2025 - Dec 2025
  • Estimated project cost $115,000
  • Australian Government contribution $115,000
  • Local Council/Shire Leeton Shire Council
  • State NSW

Project description

Road width and poor crossfall drainage for asset maintenance are the two main contributing factors for the inclusion of Boronia Road into the R2R program. The existing pavement is narrow and in poor condition with reverse crossfall, leading to increased water ponding and increased maintenence requirements. the road requires continued edge repairs and general pavement and surface defect repairs.

Works will include full pavement rehabilitation with pavement widening, subgrade stabilisation and crossfall correction, works will be completed with a 2 coat bitumen seal.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.