• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Aug 2013 - Oct 2013
  • Estimated project cost $210,564
  • Australian Government contribution $180,137
  • Local Council/Shire Singleton Council
  • State NSW

Project description

Pavement has failed and sealed surface is rough to drive, water ponds in deperessions .

In situ mix of existing and new pavement material, compact and seal.

Total cost of proposed project is $210,564

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.