• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Jun 2014 - Aug 2014
  • Estimated project cost $1,480,000
  • Australian Government contribution $587,696
  • Local Council/Shire Town of Port Hedland
  • State WA

Project description

Traffic volumes have increased significantly and has resulted in congestion in this location where dual lanes merge to single lanes. Turning into Hamilton road has been hampered by the increased traffic, which will become worse once the new Recreation Facility is built (early 2012) providing an additional access point onto Hamilton road. Traffic will need to be controlled at this point.

Widen this section of Hamilton road to construct dual lanes to match existing dual lanes on either side of this section of road. A new roundabout will be constructed at the new intersection of Hamilton road and Recreation Facility entrance to control traffic flows and conjestion.

Total cost of proposed project is $1,480,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.