• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish May 2013 - Aug 2013
  • Estimated project cost $720,000
  • Australian Government contribution $457,290
  • Local Council/Shire Warren Shire Council
  • State NSW

Project description

Existing sealed road pavement has failed (rutted, extensive potholes) and single lane seal width is dangerous for traffic.

Proposed to rip existing 3.6 metre seal. Widen formation to 8.4 metres. Overlay 300mm gravel and bitumen seal to 7 metres. Length of Work 4.7km. Total Cost $720,000.

Total cost of proposed project is $720,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.