• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish May 2013 - Jul 2013
  • Estimated project cost $150,000
  • Australian Government contribution $75,000
  • Local Council/Shire District Council of the Copper Coast
  • State SA

Project description

Deteriorating pavement, insufficient lane width and this will be the last stage of the complete road works upgrade of Drain Road.

complete reconstruction involving kerbing on one side, improved shoulder on opposite side and complete pavement reconstruction involving seal.

Total cost of proposed project is $150,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.