• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Apr 2013 - Mar 2014
  • Estimated project cost $1,450,000
  • Australian Government contribution $307,079
  • Local Council/Shire Department of Territory & Municipal Services
  • State ACT

Project description

Reconstruction of the shared path that was washed out during extreme weather events over the 2010/11 and 2011/12 summer periods.

Reconstruct approximately 300m of the shared path utilising a new twin span bridge structure (recycled steel pedestrian bridge) and approaches. Also reconstruction of the river bank and retaining wall foundations impacted by the washout.

Total cost of proposed project is $1,450,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.