• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Oct 2013 - Jul 2014
  • Estimated project cost $436,525
  • Australian Government contribution $353,769
  • Local Council/Shire Central Darling Shire Council
  • State NSW

Project description

The road at this location has been washed away and resulted in prolonged road closures in times of moderate flooding and high rainfall events.

Install new precast reinforced concrete box culverts at 2 locations on Yampoola watercourse 120m apart. Works to include rip rap scour protection, batter stabilisation and new guardrailing

Total cost of proposed project is $436,525

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.