• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Dec 2013 - Jun 2014
  • Estimated project cost $2,540,000
  • Australian Government contribution $380,035
  • Local Council/Shire Wollongong City Council
  • State NSW

Project description

Major geotechnical rockface and slope instability which is causing rock falls onto the road and landslip within sections of the road.

Design and construction of up hiil rock face/slope stabilisation works, surface and sub- surface drainage infrastructure, reconstriction of sections of road embankment and replacement of damaged sections of asphalt road surface.

Total cost of proposed project is $2,540,000

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.