• Funding program Roads to Recovery Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Nov 2013 - Dec 2013
  • Estimated project cost $42,423
  • Australian Government contribution $42,423
  • Local Council/Shire Narrandera Shire Council
  • State NSW

Project description

loose stones on the road surface, big size rock protruding on the road , hazardous , several complaint about the road roughness and safety issues

Rehabilitation, Rip the road , bring fines from the shoulder and compact it with 15 T padfoot roller to break big sized rocks on road and finish with smooth drum roller

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.