• Funding program Investment Road and Rail Program
  • Status Completed
  • Transport mode Road
  • Expected start/finish Late 2014 - Late 2015
  • Estimated project cost $10,788,227
  • Australian Government contribution $8,000,000
  • State NT

Project description

The project involved sealing sections of the Santa Teresa Road and the installation of a concrete floodway across Yam Creek crossing.

Benefits

The project aimed to improve flood immunity, safety and reliability, while also providing increased efficiency and productivity for both freight vehicles and other road users.

Funding

The Australian Government has contributed $8 million towards this project.

Timetable

Works commenced in late-2014, and were completed in December 2015.

Project last updated:

Disclaimer: The material contained in this site is made available on the understanding that the Department is not thereby engaged in rendering professional advice for a particular purpose. Before relying on the material in any important matter, users should carefully evaluate the accuracy, completeness and relevance of the information for their purposes and should obtain appropriate professional advice relevant to their particular circumstances.